DPW Weekly Construction Update
Week of September 14, 2026 – September 18, 2026
- ADA Ramps – Replacing (Contractor)
- Catch Basin Cleaning
- Concrete Work (Miscellaneous)
- Lawn Damage Repair
- Road Patching
- Sidewalk Replacement
- Barker St. – Prepping for Paving
- Clark St. – Prepping for Paving
- Clarke Ave. – Digging & Pouring Curbs (Contractor)
- Cowing St. – (Haywood to Frink) – Paving
- Douglas Ave. – Prepping for Paving
- E. 2nd St. – CATCO Working on Infrastructure Work & Concrete Work
- Ellicott St. – Paving Base & Grading for Blacktop
- Frink St. – Digging & Pouring Curbs (Contractor)
- Isabella Ave. – (Monroe to Jefferson) Shoulder & Drainage Work
- Jones & Gifford Ave. – Ditch Cleaning w/Chautauqua County
- Marion St. – Paving
- Valleyview Ave. – Storm Repair Work
*For current weekly activity and updates, please reference the schedule above.















