Week of June 27 – July 1, 2022
- Street sweeping
- Partial reconstruction of Tower St., King St. to English St.
- Waiting for NFG to begin gas main work
- Sciota Street – Contractor installing curbing
- Street Patching
- Misc. concrete work
- Catch basin cleaning
- Clearing site for kayak launch on Clifton Street
- Washington Street: 17th St. to 22nd St.
- Lake Shore Paving continuing with the water main installation
- CATCO continuing traffic signal work
- Barrett Ave. / Baker St. Reconstruction and Realignment
- Waiting for contractor to install new sidewalks
- Finishing catch basin tops
- Paving water ditch on May Street doing catch basin work
- Grindline continues work on the new Skatepark
- Chip Seal to begin the week of June 27th
- Novachip to begin the week of June 27th
- Pave prep on Newton Avenue
- Installing storm line on Emory Drive
- Prepping to top Fairfax Rd.